Surface Water Management & Norfolk Turkey’s Nest

FMG engaged TCD to install several culverts across two new haul roads within their Christmas Creek and Cloudbreak Mine Sites.

Cloudbreak required five culvert locations, with sizes ranging from 600mm diameter to 1,500mm diameter, and a cumulative length of 672m. While over at Christmas Creek there were six locations, with sizes ranging from 900mm diameter to 1,500mm diameter, and a cumulative length of 1,416m.

What started as a straightforward job grew in scope while we were on-site and, thanks to our range of services, we were quickly able to take on additional works, which included Access Track Upgrades and the installation of a Turkey’s Nest.

The works for the 3 ML Turkey’s Nest included the supporting civil pads and access tracks, the installation of geofabric and HDPE liner, float arm, fencing, signage, egress nets, life buoys and conveyor protection matting.

$3.3M

Client

FMG

Location

Pilbara, WA

Project Duration

4 Months

Project Start

July 2018

Project Finish

November 2018

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
CV006 Earthworks, Roadworks and Drainage

TCD were engaged by FMG to undertake the earthworks, roadworks and drainage for the construction of the new

PathLearn more
Vertical WHIMS Facility Upgrade – Bulk Earthworks

TCD were engaged by FMG to complete the Bulk Earthworks on Vertical WHIMS (Wet High Intensity Magnetic Sepa

PathLearn more
OPF2 Tails Line COS Bypass Construction

FMG’s Christmas Creek Mine required a 350m section of HDPE lined steel. The mine’s current OPF2 Tails L

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our civil construction contractors can make your next project a success.

Contact Us