Case Studies

Fiona Stanley Hospital Civil Works

The building and completion of Fiona Stanley Hospital has been one of WA’s most important construction projects in recent years. TCD was engaged by Downer Edi on this government funded project because of our range of services, expertise, and reputation for delivering on time.

We were responsible for the drainage, sewer, water and gas underground services. This included the installation of six large underground soak wells, one of which was the largest built in the southern hemisphere, coming in at 1.5 cubic hectares.

Often, in big projects it’s the little things that make a big difference. TCD worked collaboratively with the principal contractors for site access to their area of works and the use of the site crane. This simple approach meant all timelines were kept to, and the works being delivered on schedule.

$8.7M

Client

Downer Edi

Location

Murdoch, WA

Project Duration

17 Months

Project Start

March 2010

Project Finish

August 2011

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
CV006 Earthworks, Roadworks and Drainage

TCD were engaged by FMG to undertake the earthworks, roadworks and drainage for the construction of the new

PathLearn more
Vertical WHIMS Facility Upgrade – Bulk Earthworks

TCD were engaged by FMG to complete the Bulk Earthworks on Vertical WHIMS (Wet High Intensity Magnetic Sepa

PathLearn more
OPF2 Tails Line COS Bypass Construction

FMG’s Christmas Creek Mine required a 350m section of HDPE lined steel. The mine’s current OPF2 Tails L

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our civil construction contractors can make your next project a success.