BHP South Flank Y2 Multiplate Culvert Install

While we were working with NRW Civil and Mining, installing culverts on BHP’s South Flank Construction Project, BHP requested the installation of an additional DN2400 multiplate culvert on the Southern Haul Road of the project.

This was no ordinary culvert. It measured 165m long and we needed to place the riprap to headwall and culvert apron as part of the variation. We completed the project on time and on budget and used a staggering 10,000 bolts.

$330K

Client

NRW Civil and Mining

Location

Pilbara, WA

Project Duration

1 Month

Project Start

March 2019

Project Finish

April 2019

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
CV006 Earthworks, Roadworks and Drainage

TCD were engaged by FMG to undertake the earthworks, roadworks and drainage for the construction of the new

PathLearn more
Vertical WHIMS Facility Upgrade – Bulk Earthworks

TCD were engaged by FMG to complete the Bulk Earthworks on Vertical WHIMS (Wet High Intensity Magnetic Sepa

PathLearn more
OPF2 Tails Line COS Bypass Construction

FMG’s Christmas Creek Mine required a 350m section of HDPE lined steel. The mine’s current OPF2 Tails L

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our civil construction contractors can make your next project a success.

Contact Us